How long will it take to build out the network, and when will services be available?

The next steps from NorthState are to formulate a more detailed engineering plan, which will take several months. The entire build – including the RFP and NorthState's privately financed portion – is scheduled to be finished by the end of 2025, barring unforeseen circumstances.

The construction timeline would make services available to homes within the RFP according to the following schedule:

PhaseHomes addedDate
12,000April 2023
22,000July 2023
32,000October 2023
42,000January 2024
51,000April 2024
6898July 2024